| Description | PAN 58 - Environmental Impact Assessment |
|---|
| ISBN | n/a |
|---|
| Official Print Publication Date | |
|---|
| Website Publication Date | October 18, 1998 |
|---|
Contents |
Listen
PAN 58 - Environmental Impact Assessment
September 1999
Introduction
1. Environmental Impact Assessment (EIA) is a process
which identifies the environmental effects (both negative
and positive) of development proposals. It aims to prevent,
reduce and offset any adverse impacts.
2. Within the overall EIA process there are 2 main
stages. In the first stage the applicant undertakes an
assessment so that environmental issues can be taken into
account during the design of the project. This involves
consultations, data collection and environmental studies to
identify the effects and propose mitigation measures to
prevent, reduce and offset them. This is reported in an
environmental statement (ES) which is submitted in
conjunction with the planning application. The planning
authority then undertakes the second main stage by
critically evaluating the statement, seeking further
information from the applicant if necessary and taking into
account additional consultations and public
representations. This is to ensure the planning authority
has sufficient reliable information to understand the
likely environmental effects and specify any mitigation
measures before the planning application is determined.
3. The types of project for which an EIA has been
undertaken are typically complex, with a wide range of
environmental effects. They often occupy extensive sites
and are in sensitive locations. They are likely to raise
issues which are not always easy to resolve and which often
attract contentious representations. For such projects EIA
provides a systematic approach to obtaining and considering
environmental information.
4. The statutory requirement for EIA applies to the
types of projects described in the Environmental Impact
Assessment (Scotland) Regulations 1999 (Schedules 1 and 2).
EIA is always required for a Schedule 1 project which by
virtue of its nature or scale is always likely to have
significant environmental effects. EIA is only required for
a Schedule 2 project if it is judged likely to have
significant environmental effects. For the overwhelming
majority of development projects however, normal planning
powers are perfectly adequate to gain environmental
information and EIA is not required (see paragraphs
10-12).
Schedules 1 & 2 are reproduced at Annex 1 &
2
5. This PAN provides information and advice on:
- the legislative background to EIA;
- EIAs in Scotland;
- the process of environmental impact assessment
;
- environmental studies and statements;
- the evaluation of environmental information by the
planning authority;
- implementation through the planning decision.
6. It also points the reader to additional sources of
information and advice. Guidance and advice on EIA in
relation to specific topics has already been issued in
relevant NPPGs and PANs which should be read in the light
of this PAN, the 1999 Regulations and SEDD Circular
15/1999. An index to the EIA references in NPPGs and PANs
is at Annex 3.
7. This PAN relates specifically to environmental impact
assessment for development projects authorised under
planning legislation. EIA may be required under other
legislation, for example trunk roads under the Roads
(Scotland) Act 1984, but the basic principles of this
advice are likely to be relevant. Further information on
other regimes may be found at paragraphs 102-104.
The term EIA was formerly known as Environmental
Assessment (EA).
The Legislative Contex
The European EIA Directive and The Scottish
Regulations
8. The statutory requirement for environmental impact
assessment is the 1985 European Council Directive (No.
85/337/EEC) "on the assessment of the effects of certain
public and private projects on the environment". This was
amended in 1997 by Council Directive 97/11/EC. (An informal
consolidation of the Directives is available via the
Department of the Environment, Transport and the Regions
home page -
http://www.planning.odpm.gov.uk/
.
"...the assessment procedure is a fundamental instrument
of environmental policy as defined in Article 130r of the
Treaty and of the Fifth Community Programme of policy and
action in relation to the environment and sustainable
development.....Community policy is based on the
precautionary principle and on the principle that
preventative action should be taken, that environmental
damage should as a priority be rectified at source and that
the polluter should pay."
EC Directive 97/11/EC
9. The Environmental Impact Assessment (Scotland)
Regulations (Scottish Statutory Instrument 1999 No. 1)
transpose the EIA Directive as amended into Scottish
planning law. With regard to Town & Country Planning
matters they supersede the Environmental Assessment
(Scotland) Regulations 1988 and all amendments. The
Regulations set out the statutory procedures, list the
types of project to which they apply, specify the
information to be contained in an environmental statement,
list the consultation bodies and provide criteria for
deciding whether projects are likely to have significant
environmental effects. Copies of the Regulations may be
purchased from The Stationery Office and are also available
on their web site (
www.scotland-legislation.hmso.gov.uk).
Environmental Information and Normal Planning Powers
10. The Town and Country Planning (Scotland) Act 1997
and the General Development Procedure Order 1992 provide
planning authorities with wide ranging duties and powers to
collect and evaluate information from consultees and the
applicant before determining any planning application. This
may involve consultation and discussion as appropriate with
statutory bodies (such as the Scottish Environment
Protection Agency and Scottish Natural Heritage), amenity
bodies, community councils, the public generally and other
council departments or services.
11. The planning system therefore provides a means for
assessing the environmental effects of all applications and
the absence of a formal EIA does not mean that
environmental issues are not being considered nor
appropriate mitigation measures put in place. In the vast
majority of cases, the normal powers and duties are
sufficient for the planning authority to gather the
information it needs, but when an EIA is required, they are
supplemented by the procedures set out in the Environmental
Impact Assessment (Scotland) Regulations 1999.
12. A wide range of development proposals have
'permitted development rights' which means that a specific
application for planning permission is not needed. Where
however such proposals require EIA under the Regulations,
permitted development rights are withdrawn and planning
permission must be sought. In cases of doubt the planning
authority should be consulted.
Circular No. 15/99 paragraphs 61-65
Other Environmental Legislation
13. There are additional environmental controls which
are likely to share information requirements with an EIA.
These include Integrated Pollution Control which deals with
discharges from major industrial processes and the Control
of Major Accident Hazards Regulations. Each has its own
legislative requirements and questions will arise over
whether applications should be prepared and submitted
concurrently or sequentially. For further advice reference
should be made to PAN 51 Planning and Environmental
Protection (paragraphs 45 - 48).
14. EC Directive 96/61 on Integrated Pollution
Prevention And Control (IPPC) was adopted in September
1996. Although the directive's provisions do not require
that an EIA be prepared for IPPC authorisation, if an EIA
has been carried out under the EIA (Scotland) Regulations
then that information may be included in or attached to the
application. (The IPPC Regulations which will implement EC
Directive 96/61 are intended to come into force on 30
October 1999)
15. Special Protection Areas (SPAs) under the EC Wild
Birds Directive (79/409/EEC) and Special Areas of
Conservation (SACs) under the EC Habitats Directive
(92/43/EEC) are collectively known as "Natura 2000" sites.
Planning authorities are required to make an appropriate
assessment of whether a plan or project significantly
affecting a Natura 2000 site is likely to damage a
conservation interest of that site, and in doing so they
must consult SNH. The assessment is required whether or not
the proposal is subject to a full EIA. If an EIA is carried
out for a project affecting a Natura 2000 site, the
environmental statement should address the impact of the
proposal on the conservation interest of the site in
question. The environmental statement will help the
planning authority to make its assessment of whether a
proposal is likely to have a detrimental effect on the
conservation interest and therefore whether they may grant
planning permission for the proposal. The Government's
policy is that proposed Natura 2000 sites, and sites
designated under the Ramsar Convention on Wetlands of
International Importance, should be protected to the same
extent as if they had the status of designated SPAs or
SACs. Further advice is given in SOEnvD Circular No.
6/1995.
Record of EIA in Scotland
Background
16. Scotland was in the forefront of environmental
impact assessment during the 1970s and early 1980s when
around thirty were undertaken, predominantly for the large
onshore construction projects associated with the North Sea
oil and gas industry. This work, supplemented by experience
in the rest of the UK and by practice in the United States
was drawn together and published in A Manual for the
Assessment of Major Development Proposals, London, HMSO,
1981. The aim of the manual was "to assist planners and
others in making a balanced assessment of major development
proposals within the existing framework of planning
controls and other statutes."
Number & Types of EIAs
17. Since the 1988 Regulations came into force, the
procedural requirements for environmental impact assessment
have been fully integrated into the operation of the
planning system. In Scotland up to February 1999, there had
been 347 EIAs for planning projects. To put this figure
into context, in the year from April 1998-March 1999 there
were 42,432 planning applications in Scotland.
18. Of the 347, only 27 were for Schedule 1 projects
(for which EIA is always required). Table 1 shows the
number of Schedule 1 projects by category:

19. Schedule 2 of the 1988 Regulations contained 85
categories of project. More than two-thirds of the EIAs in
Scotland were however undertaken for projects in only 8 of
these categories (see Figure 1). There were no planning
related EIAs for the majority of categories.

20. Of the eight most common project categories, the two
types of mineral extraction (which may often generate
similar large scale environmental effects) have accounted
for around 27% of the total number of EIAs since 1988.
Controlled waste disposal (i.e. household, commercial and
industrial waste disposal) accounted for nearly 12%, and
wind generators around 8% despite the fact that this
category was only added to Schedule 2 in 1994. The
implementation of various European Directives relating to
water quality explains the number of waste water treatment
works (7%). Urban development projects (5%) included
football stadia, new settlements and mixed use development
projects.
Distribution of EIAs
21. Map 1 shows the distribution of EIA applications.
There is a marked concentration in the Central Belt where
population and development pressure is greatest, and on the
east coast. Highland, Fife and East Ayrshire have had a
large number of applications whilst neither East
Dunbartonshire nor East Renfrewshire have received any (see
table 2). Authorities' experience of handling EIA
applications consequently varies accordingly.

22. Certain projects have specific requirements that
dictate their location. The presence of a particular
resource within an authority's boundary will affect the
categories of project with which it is likely to be
familiar. For example, of the 27 EIAs carried out in East
Ayrshire (and its predecessor authorities), 60% relate to
opencast coal applications.

23. A list of environmental statements received by the
Secretary of State for planning projects is included at
Annex 4. This may be useful to both planning authorities
and other interested parties where they are faced with
unfamiliar projects, so that they may draw on relevant
experience that exists elsewhere in Scotland. The
statements are available for examination by arrangement
with the Scottish Executive Library, K Spur, Saughton
House, Edinburgh (Tel. 0131 - 244 4564).
EIA overview
24. The process of EIA should begin when a project is
initiated and continue right through to monitoring the
impacts of the development, the on-going operation of
mitigation measures and, where appropriate, site
restoration. The process includes the preparation of an
environmental statement by the developer to accompany a
planning application, consultation with expert bodies and
the public, and scrutiny by the planning authority. In this
way the available information about the environmental
effects of a project is collected and evaluated before
being taken into account in the determination of the
planning application.

25. The overall EIA process may be subdivided into a
number of steps, illustrated by the adjacent diagram. The
diagram is a simplified depiction of a complex process. In
practice, the process rarely proceeds in a simple linear
fashion. For example, environmental studies may identify a
significant adverse impact which can only be overcome by
altering the design, so the process reverts to the first
step, but this does not necessarily mean that the screening
and scoping stages will have to be repeated.
Consultation and Public Involvement
26. At several steps in the EIA process, a number of
bodies have a duty if requested to provide information and
advice: to the planning authority on the scope of the EIA,
to the applicant during the preparation of the
environmental statement (ES), and to the planning authority
during their evaluation of the ES and consideration of the
application. During the EIA process, as additional
information is made available the initial views of
consultees may develop, but there is an expectation that
their advice will be consistent on points of principle. As
appropriate in giving their advice these bodies act within
the requirements of their own legislation to
protect/promote the well being of the environment. The
consultation bodies and their areas of expertise are set
out in the box below.

EIA (Scotland) Regulations1999, Regulation 2(1)
27. There is also a requirement for public involvement.
The submission of an environmental statement must be
advertised and copies made available for inspection or
purchase at reasonable cost. Local and national interest
groups, and members of the public may all have useful
comments to make on the scope of the assessment, the
existing environment, potential impacts and mitigation
measures. Local knowledge may raise issues of which the
statutory bodies are unaware, and for this reason,
notwithstanding the statutory consultation requirements the
public should be invited to participate in the process as
early as is possible. Public meetings, leafleting of local
residents and questionnaires have all been used to elicit a
comprehensive understanding of public views and
concerns.
Circular No. 15/99 paragraphs 101-110
Outline applications
28. Where EIA is required for a planning application the
requirements of the Regulations must be fully met
regardless as to whether the application is in outline
form. The limited information generally provided in an
outline application is unlikely to be sufficient to form
the basis of an environmental statement (ES), or for the
planning authority, the public and the statutory consultees
to make an informed response. There may be uncertainties
for example over the way the project will be constructed
and operated, including its design and development
footprint, making it difficult to accurately determine the
environmental effects on the basis of the documentation
submitted with the outline planning application. Further
environmental information will thus be required to ensure
compliance with the regulations.
Circular No. 15/99 paragraph 48
29. There is no completely satisfactory approach to
resolving the uncertainty inherent in technically complex
projects. Attempts have been made to base the work on a set
of assumptions about the project and the resultant effects.
The EIA might proceed on that basis with the detailed
design of the project being undertaken within the
parameters set by the assumed impacts as a whole, allowing
for some trade-offs between the detailed impacts. If
however it was subsequently found that the detailed design
could not proceed within the set of assumptions, a new EIA
might be necessary under Schedule 2 paragraph 13 which
covers changes or extensions to projects. Alternatively,
applicants have agreed at the outline stage to abide by the
environmental performance and mitigation measures which
will be defined at the detailed stage as being "to the
satisfaction of the planning authority".
30. Either option will pose difficulties:
- for the applicant, who will be entering into a
project with uncertain mitigation and perhaps design
costs;
- for the consultees and public who will be unable to
fully contribute; and
- for the planning authority who will have to
determine an application that by definition is likely
to have significant environmental effects but which
will, at best, be only partly defined.
A planning authority may decide, given the circumstance
of a case, that they are unable to entertain an outline
application unless further details concerning the siting,
design, external appearance, access or landscaping have
been submitted (Article 4(3) of the General Development
Procedure (Scotland) Order 1992).
31. In considering whether an outline application
accompanied by an ES can be entertained, planning
authorities and developers should bear in mind whether:
- enough detail is known about the project to prepare
an ES in accordance with Schedule 4 of the Regulations,
particularly the description of the development and the
processes, and to give 'an estimate by type and
quantity of expected residues and emissions';
- for the particular project, an ES based on an
outline application is consistent with the principle of
project design and environmental considerations
progressing together;
- the public's ability to make representations will
be unduly constrained;
- the complexity of the likely environmental effects
can only be properly explored at the detailed
stage;
- an outline will provide sufficient information for
the planning authority to determine the
application.
EIA (Scotland) Regulations1999, Schedule 4, Part
I,1(c)
Project Initiation - Design with the Environment
32. Environmental issues should be considered at the
earliest stages of a project, such as project initiation
and feasibility studies, alongside the other design and
technical factors. Design work should proceed in the
knowledge of any environmental constraints and issues.
Consideration of environmental issues at all stages of
project development is likely to prevent costly mistakes,
for example abortive design work, which could have been
avoided if the environmental constraints had been realised.
Such consideration should also result in the cost-effective
design of mitigation measures and may help to identify
positive impacts which will enhance the environment.
33. Providing environmental data to inform project
design is a key function of EIA, for example a landscape
assessment may suggest the optimum position for siting
buildings to minimise their impact on the landscape. The
detail contained in the EIA will increase as the project
progresses and can be used iteratively in the design
process. One application of EIA is in the initial site
selection process, where the information obtained through
scoping can be used to prevent impacts by choosing a site
(or sites) which avoids environmentally sensitive features
(see paragraphs 53-54 on mitigation).
34. The environmental issues should also influence the
alternatives considered and be key factors in choosing
between them. The alternatives may include different sites,
different positions of buildings, plant and equipment on
the site, or different processes. Once a preferred site is
selected, detailed EIA can then be used in conjunction with
design to provide acceptable site layouts and operational
processes. For example, the ES for a proposed waste to
energy plant in West Lothian reviewed alternative disposal
options for clinical waste (including export to existing
sites in England), as well as alternative sites in Central
Scotland.
Screening - Considering Whether EIA Is Required
35. The planning authority has a statutory
responsibility for deciding whether an EIA is required for
Schedule 2 projects (an EIA is always required for Schedule
1 projects) - a process known as 'screening'. Initially
however the applicant should consider, possibly in
discussion with the planning authority, whether in their
view a project requires EIA. Firstly it must be a "Schedule
2 development" i.e. it must be listed in Schedule 2 of the
Regulations and either exceed or meet any applicable
threshold or criterion in Column 2 of that schedule, or be
in a 'sensitive area' (as defined in the Regulations Part
II, 2(1)). Once a proposal is established as a Schedule 2
development, to require an EIA it must be judged by the
planning authority as
likely to have significant environmental
effects. A written request may be made to the
planning authority for their opinion. The characteristics
of the development, its location and potential impact are
key considerations, and detailed criteria under these
headings are set out in Schedule 3 of the Regulations.
EIA (Scotland) Regulations1999, Schedule 2
Circular No. 15/99 paragraphs 28-49
36. In the light of the criteria EIA will generally be
needed for Schedule 2 projects in three main types of
case:
- Major developments which are of more than local
importance;
- Developments which are proposed for particularly
environmentally sensitive or vulnerable locations;
- Developments with unusually complex and potentially
hazardous environmental effects.
For Schedule 2 developments the need for EIA has to be
determined on a case by case basis. To assist in this the
Circular lists indicative criteria and thresholds which
indicate the types of case for which EIA is more likely to
be required.
Circular No. 15/99 Annex A
37. Only limited information about the project may be
available initially, though the planning authority may
request additional information. The planning authority may
occasionally wish to seek the advice of key consultees, but
nevertheless experience shows that it can sometimes be
difficult to reach a decision on the need for EIA. In such
cases, and within the requirement to undertake EIA for
projects where there are likely to be significant
environmental effects, the considerations which affect the
planning authority's decision on whether EIA is required
have included:
- whether EIA is the only way to be certain of
gaining the environmental information;
- whether the potential impacts are limited, with
negligible interaction between them;
- the complexity of any interdependent impacts;
- the proximity of, and possible effects on,
designated areas and sensitive receptors; and
- where an EIA would remove uncertainty and improve
confidence that environmental issues have been fully
addressed.
For detailed guidance on Screening reference should be
made to SEDD Circular No.15/99, paragraphs 28-79.
Environmental Studies
38. EIA has to identify the likely environmental effects
of a project through the study and analysis of individual
issues, predicting and assessing the projected impacts and
proposing measures to mitigate the effects. The work is
invariably led by a consultant or in-house team, calling
upon experts in particular fields (e.g. noise) to undertake
specific studies and advise on mitigation measures. The
statutory consultation bodies have a duty to provide
information if requested and may also on occasion be able
to advise more widely on such issues as design and
construction. In addition, applicants may find it
beneficial to keep the planning authority informed as the
work progresses on the studies and environmental statement,
offering them the opportunity to comment.
EIA (Scotland) Regulations1999, Regulation 12
39. The approach to any assessment and the techniques
employed will be dependent on the nature of the project,
potential impacts and the environment. However, the
approach and its presentation in the ES should always be
systematic.
A Systematic Approach
Scoping(see paragraphs 40-43)
- undertake a scoping exercise to establish
significant issues
Baseline Studies (see paragraphs
44-46)
- examine, through baseline studies, the
environmental character of the area likely to be
affected by the development;
- identify relevant natural and manmade processes
which may already be changing the character of the
site;
Predicting and Assessing Impacts (see
paragraphs 47-52)
- consider the possible interactions between the
proposed development and both existing and future site
conditions;
- predict and assess the possible effects, both
negative and positive, of the development on the
environment; and
Mitigation (see paragraphs 53-57)
- introduce design and operational modifications or
other measures to avoid, minimise or mitigate adverse
effects and enhance positive effects.
(Source: paragraph 1.2, Preparation Of Environmental
Statements For Planning Projects
That Require Environmental Assessment- A Good
Practice Guide, DOE, 1995)
Scoping
40. The applicant should identify the key issues for EIA
before the detailed studies commence (a process known as
'Scoping'). The normal pre-application discussions between
the developer and the planning authority are an opportunity
for both parties to discuss the scope of the EIA. For the
planning authority in particular, this is an opportunity to
act positively and provide early advice on the EIA process,
methodologies, sensitive issues and sources of information.
Early involvement of all parties is encouraged. Under
Regulation 10, the planning authority has a duty, if
requested, to give their opinion in writing to the
applicant on the information to be provided in the ES. The
applicant has first to provide information on the proposal
including a site plan, a brief description of the proposal
and its possible effects. At project initiation stage
developers may wish to carry out scoping to a limited
extent, possibly on a confidential basis, prior to seeking
the formal opinion of the planning authority. The scoping
is a key part of the EIA process but additional issues may
still emerge as work progresses and the planning authority
is not precluded from requiring the applicant to submit
further information at a later stage.
41. The purpose of scoping is:
- to focus the EIA on the environmental issues and
potential impacts which need the most thorough
attention;
- to identify those which are unlikely to need
detailed study;
- to provide a means to discuss methods of impact
assessment and reach agreement on the most
appropriate.
42. By drawing on the knowledge of the planning
authority and consultees, a scoping exercise will help the
developer to identify the main issues quickly. It also
gives an early indication of where mitigation measures may
be necessary and should help to reduce requests for further
information once the ES is submitted. In some cases
developers have used a forum of interested parties to
discuss the issues informally prior to the formal scoping
stage. The matters identified by the scoping exercise will
derive from the nature of the project, the site and the
environment.
43. A good scoping exercise will lay the foundations for
a good EIA. It is a critical and essential stage. Further
advice is available in
Guidance on Scoping European Community May 1996
and in
A Good Practice Guide to the Preparation of
Environmental Statements DoE 1995.
In the case of the Beinn An Tuirc windfarm in Argyll and
Bute, initial discussions with a limited range of parties
led to a preliminary scoping report which was then widely
circulated. This brought other interested parties into the
process and gave the applicant a secure basis for the
study. A summary of the issues raised by each interested
party was presented as a matrix in the ES (see Figure
2).
A consultation exercise was also carried out to identify
the most significant of the issues and detailed assessments
were carried out for:
- landscape and visual amenity
- protected bird species
- protected habitats (blanket bog)
- tourism
- noise
- telecommunications and television
interference.
Three other issues were also assessed in less
detail:
- air and climate
- transport
- archaeology

Baseline Information
44. Information on the existing environmental conditions
(i.e. baseline information) is needed so that possible
changes can be predicted and assessed. The topics for
baseline information and the methods of study should be
identified and agreed by the relevant parties in the
scoping exercise. Collecting the information may involve,
in the first instance, drawing on existing records, for
example archaeological records, but where information does
not exist or is inadequate for accurately predicting
possible impacts, new surveys will need to be undertaken
e.g. conducting a noise survey to measure the existing
noise climate. The planning authority and statutory
consultees will be of assistance in identifying data
sources and advising on appropriate measuring techniques.
Existing sources will be particularly valuable when
surveying can only be carried out at a certain time of the
year (e.g. surveys of flora or migratory birds), or must be
undertaken over a lengthy period of time (e.g. to
understand behavioural patterns). In the absence of
existing data, applicants should be aware of such time
constraints when programming projects.
45. Baseline studies should also identify the existing
processes of change in the environment which are likely to
influence the character of the site or its surrounds, so
that any changes which are predicted to occur due to the
project can be distinguished from those which are expected
to occur anyway. The predicted future environmental
conditions which would exist if the proposed development
did not materialise is known for EIA purposes as the 'do
nothing scenario'.
46. There is often more than one method of measuring
environmental information. For example, different indices
and methods are used for measuring, predicting and
assessing industrial noise as compared to transport noise.
Furthermore, there may be different levels of survey. In
the case of habitat, for example, an initial survey may
simply involve a general description of habitat, but this
may indicate that a more detailed survey is required
involving the collection of quantitative vegetation data.
The method and level of survey will be determined by the
nature of the project and the sensitivity of the
environment.
Predicting and Assessing Impacts
47. Using the information from the baseline studies and
knowledge of the proposed development, the aspects of the
project which might affect the existing or predicted
environment can be identified. The effects (positive as
well as negative) generated by the project should be
identified and evaluated for both the construction and
operational stages. It is likely that each stage will have
different impacts and in some cases the more significant
effects will be during construction. For some projects the
environmental effects will extend considerably beyond the
confines of the application site. Baseline studies and
predicted impacts should reflect this. For each
environmental topic area, types of impact identified
"should cover direct effects and any indirect, secondary,
cumulative, short, medium and long-term, permanent and
temporary, positive and negative effects". The
inter-relationship between impacts is an important
consideration. The data gathered can and should feedback
into the design process, in order that adverse
environmental impacts can be addressed at an early stage
(see paragraphs 32-34 on Project Initiation - Design with
the Environment).
EIA (Scotland) Regulations1999, Schedule 4, Part I.4
48. The majority of the work should be devoted to those
key issues which give rise to the major environmental
effects, and how they have been mitigated. It is not
usually necessary to study minor impacts in detail. Nor is
there any point in assessing impacts in detail if it has
been established that emissions fail to meet acceptable
standards. For example, if water pollution levels will
exceed legal maxima there is little point in proceeding to
report on the precise effects on aquatic flora and fauna.
An effective scoping process will identify the importance
of the issues, the method for studying them and what
standards are applicable. The scoping study for an EIA for
industrial development in South Ayrshire showed that
ecological impacts were unlikely to be significant given
that the land was already intensively farmed. Consequently,
the issue was considered in only one and a half pages in
the environmental statement. However, a similar development
in a more sensitive location, e.g. adjacent to an SSSI, is
likely to need more detailed analysis.
49. Impacts can often be analysed in terms of the source
of pollution (e.g. emissions of process water), the
pathways by which they may travel (e.g. through ground
water) to arrive at a receptor (e.g. fish or a reservoir
intake). This approach provides a useful basis for
understanding the environmental pollution impacts of
projects and identifying the measures which are needed to
mitigate them.
50. Methods for predicting environmental effects and
their magnitude are specific to the environmental topic and
are a matter for expert consultants. For some topics there
will be qualitative techniques (e.g. landscape assessment,
photomontage) which rely on previous experience and
knowledge about the consequences of a given action. For
other topics there will be quantitative techniques which
usually seek to model the natural environment and calculate
the effects of the change due to the project (e.g. the
dispersal patterns and dilution of emissions to air). Some
topics may involve a mixture of qualitative and
quantitative techniques. The predictions are very likely to
be subject to a degree of uncertainty and this should be
explained together with any assumptions on which they are
based.
51. Once impacts have been identified then they must be
evaluated. For instance studies may show that there will be
emissions to air from a proposed industrial plant. If the
emissions will not lead to an increase in gases in excess
of natural variation then the effect might be described as
insignificant. If, however, gaseous emissions will result
in detectable increases in concentrations but still below
permissible legal limits, this may be considered to be of
minor significance. Emissions which will lead to a breach
of legal limits would clearly be of major significance.
Other effects, for example landscape impacts, will require
more subjective evaluation.
52. Further information on baseline measurement
techniques, and predicting and assessing impacts for
individual environmental topics may be found in the
publication, Preparation of Environmental Statements for
Planning Projects (DoE 1995), particularly in the
appendices. There is also a considerable body of literature
on the subject. Some key references may be found in the
bibliography.
Mitigation
53. The elimination of adverse environmental impacts, or
their reduction to an acceptable level is at the heart of
the EIA process. By definition all EIA projects are likely
to have significant environmental effects and the potential
for mitigation ought therefore to be considered at every
stage of the EIA process. In determining an application the
planning authority will be concerned to know which
potential effects have been prevented, which reduced, and
which offset. Effects which cannot be mitigated should be
acknowledged. It is vital that the ES plainly describes the
mitigation measures and that the magnitude and significance
of residual impacts are clearly identified.
Mitigation Measures
In this advice measures to 'prevent' adverse effects
include measures to 'avoid' them, and measures to 'offset'
include measures to 'remedy' them.
See EIA (Scotland) Regulations 1999, Schedule 4 Part I.5
& Part II.2
54. It is helpful to consider mitigation as a hierarchy
of measures ranging from the 'best' i.e. prevention, down
to the 'worst' i.e. compensatory measures. In principle the
options at the top of the hierarchy should be considered
first and lower alternatives only considered if higher
options are not feasible. The higher level alternatives can
probably only be fully considered during the early stages
of a project.
A. Prevent - The most effective approach
will be to prevent the creation of adverse environmental
effects at source rather than trying to counteract their
effects through specific mitigation measures (e.g. so
called "end of pipe" solutions). Typical at source
solutions may include:
- the choice of site - for example a site remote from
concentrations of people or which does not affect
designated areas.
- the location of plant within the site - for example
locating the noisy plant away from noise sensitive
development.
- specification of operational equipment- for example
the use of an inherently quieter machine.
B. Reduce - If the adverse effects cannot
be prevented steps should be taken to reduce them. Methods
to reduce adverse effects include:
minimisation at source
- choice of process - for example the use of a
cleaner technology or an alternative chemical
process.
- use of low noise or vibration construction
equipment
- operating the site to minimise the production of
leachate.
abatement on site
- colour of buildings
- screen planting and landscaping
- noise attenuation measures
- reduced hours of operation
abatement at receptor
- noise insulation for houses
- relocating rare species
C. Offset - When effects remain that
cannot be prevented or reduced, they may be offset by
remedial or compensatory action such as:
- provision of environmental improvements
- provision of new opportunities for access and
informal recreation
- creation of alternative habitats
- prior excavation or study of archaeological
features.
Offsetting measures can be difficult to deliver
successfully and a sensitive approach will be needed.
Action may be needed before development commences, and may
link to other initiatives for example local bio-diversity
action plans. Planning authorities should always carefully
consider whether the adverse effects are such that there
can be no adequate means of compensation, and the extent to
which the proposed offsetting measures compensate for the
negative impacts.
Schedule of Environmental Commitments
55. To clarify exactly what mitigation measures are
envisaged it will be helpful to include a separate list of
them in the ES. This is known as the Schedule of
Environmental Commitments and could be updated as the
evaluation proceeds and be used as the basis for specifying
planning conditions. It would include both integral and
'add on' mitigation measures and identify any issues where
mitigation will be agreed at a later stage. In any event
the ES should:
- specify the effects being mitigated;
- identify the location, design and timing of the
mitigation measures;
- state the predicted effectiveness of the measures
(i.e. the extent to which the impact will be reduced);
and
- explain the monitoring arrangements.
56. The choice of mitigation measures should take
account of any potential secondary impacts. For example, a
bund to mitigate noise impact will itself have an impact on
the landscape, and may affect archaeological features.
57. Specific mitigation measures may be needed to deal
with the effects arising from each stage in the life of a
development; construction, commissioning, operation,
decommissioning, and restoration & afteruse/aftercare.
They may also include alternatives, physical design and
project management measures.
(More extensive information on mitigation is contained
in
Mitigation Measures in Environmental Statements DETR
1997)
Monitoring
58. To complete the process of EIA the actual impacts of
a project and the mitigation measures have to be monitored
and compared to those predicted. This is an essential part
of the process. It will demonstrate that the time and money
invested in the EIA by all the parties is being taken
seriously and enable corrective action to be taken if
required. It will confirm and ensure that wider
environmental aims are being met. A Schedule of
Environmental Commitments (see paragraph 55-57) will
provide a good basis for monitoring arrangements.
59. Monitoring involves checking that the development is
proceeding in accordance with the planning permission, but
also includes on-going study to show whether any defined
environmental standards or parameters (for example, related
to noise, emissions to air or water quality) are being met
during construction and when the development is in use. To
be effective the monitoring arrangements must specify what
action will be triggered if the results of monitoring show
that specified standards are not being achieved.
60. For some particularly complex projects a more
comprehensive approach to managing impacts, known as an
Environmental Management System, may be preferable. This
offers a structured approach which defines all legal and
other requirements, including those in planning conditions.
It establishes responsibilities, the monitoring procedures
and performance standards, plus review mechanisms to ensure
that the system is functioning correctly.
61. The ES and any conditions concerning monitoring
should specify:
- what is to be monitored;
- the standard or parameter to be achieved;
- who will carry out the monitoring on the
ground;
- how the monitoring is to be funded;
- who will receive the results and be responsible for
any necessary action.
The Environmental Statement
62. The environmental statement (ES) is the applicant's
statement on the project, its likely environmental effects
and the measures proposed to mitigate adverse effects. It
will also report on the information, studies, techniques
and analysis involved in the work. A systematic ES is the
most significant contribution to the planning authority's
evaluation of the environmental effects of a project even
though it is common for further information to be required
or clarification sought as a result of the authority's
review of the ES and any representations received.
63. By collecting and presenting environmental
information in a systematic fashion, the statement is of
benefit to the planning authority, consultees, the public,
interest groups and the applicant.
Content of the Environmental Statement
64. The required contents of an ES are specified in the
1999 Regulations in the following terms:
Environmental Statement - Information
Required
"environmental statement" means a statement that
includes at least -
a) a description of the development comprising
information on the site, design
and size of the development;
b) a description of the measures envisaged in order to
avoid, reduce and, if
possible, remedy significant adverse effects (mitigation
measures);
c) the data required to identify and assess the main
effects which the
development is likely to have on the environment;
d) an outline of the main alternatives studied by the
applicant or appellant and
an indication of the main reasons for his choice, taking
into account the
environmental effects;
e) a non-technical summary of the information provided
under (a) to (d) above.
EIA (Scotland) Regulations 1999 Regulation 2(1)
& Schedule 4, Part II
65. In addition the statement must include such further
information which is reasonably required to assess the
environmental effects of the development. Reference should
be made to the Regulations but in summary further
information may include:
- a full description of the project's physical
characteristics;
- a description of the main characteristics of the
production processes;
- an estimate of expected residues and emissions from
the operation of the project;
- a description of the aspects of the environment
likely to be significantly affected by the development
(in particular - population, fauna, flora, soil, water,
air, climatic factors, material assets (including
heritage), landscape and the interaction between
them;
- a description of the likely significant effects of
the development, direct, indirect, and cumulative, on
the environment;
- a description of the forecasting methods used;
- an indication of any difficulties (technical
difficulties or lack of know-how) encountered in
compiling the required information.
EIA (Scotland) Regulations1999, Schedule 4, Part I
66. The environmental statement is submitted in support
of the planning application, but is not part of the
application itself. The statement should be objective, and
information indicating negative effects should not be
omitted. Conclusions should be drawn from the data, rather
than tailored to favour the proposal, and a distinction
should be made between matters of fact, judgement and
opinion. 67. If, during the environmental studies and the
preparation of the ES, environmental effects came to light
which could not be mitigated the developer might decide not
to make the planning application. When however a project is
taken through to the planning application stage, it is only
to be expected that the ES will conclude that overall the
environmental effects, with mitigation, are not sufficient
in the judgement of the applicant to warrant refusal of
planning permission.
68. In a good quality ES it will be clear that during
the process of preparing the ES, the environmental impacts
were accurately identified and that the project design was
altered and mitigation measures introduced in order to make
the project acceptable. This is a key way in which EIA
achieves environmental objectives. The ES is not however
definitive and the planning authority, taking advice from
consultees and the public, has the task of evaluating the
ES and confirming (or not) its validity and if necessary
seeking additional mitigation measures.
Reporting on Alternatives
69. It has always been good practice for the ES to
report on the alternatives considered by the applicant and
it is a requirement of the 1999 Regulations. The reporting
has not amounted to a full ES on each alternative, even
where they have been significantly different, but has given
an outline of them and explained how the choice between
them was made (see also paragraph 34).
EIA (Scotland) Regulations 1999 Schedule 4
70. In presenting alternatives, applicants and planning
authorities need to recognise the constraints of commercial
confidentiality and the potential for creating blight,
especially where a development is part of a programme and
the alternatives are projects which may come forward in due
course.
71. The Regulations do not require the applicant to
"invent" alternatives when none has been considered
(although the lack of alternatives should be explained). It
is accepted that the alternatives available will be
constrained by economic and operational reasons. The
planning authority should determine the planning
application on the merits of the proposal before them and
not on the merits of potential alternatives (for some
projects however the existence or otherwise of a feasible
alternative may be a material consideration in the
determination of the application).
Presentation of the Environmental Statement
72. An environmental statement should have a minimum of
two parts; a main report, and a non-technical summary
(NTS). Specific environmental studies and technical
material can be part of the statement or they can be in
separate volumes. They should however be available to
interested parties.
Main Report
73. The main report should give an account of all the
environmental assessment work from project inception
through to the mitigation measures and monitoring
arrangements. It should read as a single document and not
be merely a compendium of separate reports on each
environmental topic or impact. To help the reader, lengthy
or detailed supporting studies should be confined to
appendices, and accurately summarised in the main report
and the non-technical summary. The main body of the
statement can thus be kept to manageable proportions.
74. As each project is unique it is not appropriate to
prescribe a fixed length for statements, but in every case,
what is required is a concise, comprehensive and objective
report. About 50 pages for projects with few significant
impacts and about 100 pages where there are more complex
issues, can be taken as a general guide however. 150 pages
should generally be regarded as the maximum.
75. It is helpful if each environmental topic is
discussed in the ES in a logical sequence distinguishing
between:
- Potential impacts;
- Existing baseline conditions;
- Predicted impacts, giving a measure of their
nature, extent and magnitude;
- The scope for mitigating adverse effects; and
- The significance of unavoidable and/or residual
impacts.
76. Suitable diagrams and illustrations should be used
to support the text. Summary tables like that shown at
Table 3 are a useful way of presenting a large amount of
information in a user friendly manner.

77. The information should be presented in such a way
that the links between the main body of the report, the
appendices, and the non-technical summary are clearly
indicated, so that the reader can move from one to another
with ease. Page and paragraph numbering should be
consecutive and consistent between different sections of
the main report. If separate volumes are used, then each
should be clearly marked as to its contents. Planning
applications and environmental statements should not be
bound together in one volume, because the statement and the
planning application may be seen as one and the same thing.
In fact the EIA is only one aspect of determining a
planning application and there are likely to be other
material planning considerations.
Non-Technical Summary
78. The purpose of a Non-Technical Summary (NTS) is to
ensure that the key points of the environmental statement
including the findings of the studies and the mitigation
measures proposed can be more readily understood by
non-experts and decision makers. It should therefore be
presented in a form that does not deter the reader, and
provide an accurate and balanced statement of key
information contained in the main body. The nature of EIA
means that the ES will contain complex information, but the
NTS should present information in a manner which the lay
person may readily understand. Appropriate maps, diagrams
and illustrations should be included. Despite their name,
some NTSs have been too technical to be of use to many
members of the public and that represents a waste of time
and limited resources.
The
Non Technical Statement prepared by East
of Scotland Water, accompanying the environmental statement
for the Newbridge Waste Water Treatment Works, contains the
following helpful elements:
It is:
Size A4;
Black and white (for ease of copying);
Separately bound;
Not reliant on technical jargon; and
Structured in a logical and easy to follow way.
It includes:
A summary table of impacts; and
A site plan.
The main report also contains a copy of the NTS for ease
of reference.
79. The preferred paper size for the NTS is A4 so that
it may be easily copied for consultation and public
participation. Ideally it should be available separately as
well as being included in every ES. Consultation will be
aided if it is available free of charge. It should also say
where the complete ES may be consulted or obtained and the
cost. The NTS could also be published on the Internet.
Checklist of Quality Indicators
80. There is no one 'correct' way of preparing an
Environmental Statement, as the nature of projects, sites,
environments and methodologies vary. Nevertheless, the
following checklist should be of help to those preparing,
commenting on and evaluating statements.
Environmental Statements: A Checklist of
Quality Indicators
- Does the statement report on a systematic approach
to the gathering and analysis of information?
- Does it contain the information specified in
Schedule 4 of the Regulations?
- Is the information presented in a clear,
comprehensive and objective manner?
- Is there a relatively concise main report which
draws on the technical studies and summarises them as
necessary?
- Is there sufficient cross referencing for the
reader to make the links between the NTS, the main
report, appendices, and any separate studies?
- Is the space devoted to environmental issues
commensurate with their potential impacts, and are
those issues with insignificant impacts
identified?
- Are mitigation measures presented as a
hierarchy?
- Are mitigation (and restoration) measures described
in sufficient detail and timetabled?
- Does it state the means by which monitoring will be
carried out?
- Are the methods by which the analysis was carried
out and the ES prepared explained, and are the
credentials of the experts involved stated?
- Is the development plan context for the project set
out ?
- Are detailed technical studies contained in
appendices?
- Are links to other consent regimes clearly
indicated?
- Is the 'Non Technical Summary' a summary in
every-day language?
evaluating the environmental statement and
information
The Process of Evaluation
81. The ES is the most visible part of the whole EIA
process, and ought to be the main source of environmental
information available to the planning authority. Evaluation
however, involves not only reviewing the information and
analyses in the ES, and adding to it if necessary, but also
considering representations from consultees and the public,
plus the information provided by the council's own
specialists, and the expertise of planning officers. The
evaluation involves a process of re-interpretation and
reconsideration in the light of the representations, to the
point where the planning authority has sufficient
confidence in the nature of the likely impacts and the
necessary mitigation to determine the application and
attach any conditions. As the work progresses new issues
may come to light or need to be pursued in more depth with
the applicant. A thorough scoping exercise and a good
environmental statement will minimise the likelihood of
this. Exceptionally the full evaluation of a particular
issue will involve a second cycle of consideration but the
planning authority should consider it has sufficient
environmental information when:
- the scale and importance of each impact (e.g.
emissions to air) is known or any remaining
uncertainties are unlikely to be reduced; and
- the effects of each impact on specific aspects of
the environment (e.g. human beings) is known or any
remaining uncertainties are unlikely to be
reduced.
82. An ES and related information will present the
planning authority with a large amount of information to
manage and evaluate. In general, planning authorities do
not use formal techniques of evaluation such as Cost
Benefit Analysis. Research has shown that for EIA purposes
such techniques can have technical shortcomings and
planning officers often have reservations about their
practicability. These arise because of the diverse nature
of environmental impacts, some of which can be measured
(e.g. area of land developed), many of which cannot (e.g.
visual impact) and the absence of a formal method which can
combine all the impacts to produce an overall conclusion.
Nevertheless, specific analytical techniques may have a
role to play in clarifying individual issues, and advice is
available in
Good Practice on the Evaluation of Environmental
Information for Planning Projects - Joint Scottish
Office/DOE Research Report DOE, 1994.
83. It is important that the planning authority takes a
systematic, thorough and meticulous approach to the
evaluation. The task can be complex, particularly for major
projects where the impacts are potentially numerous, of a
technical nature and where significant new information
becomes available during the course of the work.
84. Upon receipt of the ES the case officer should read
the NTS to become familiar with the general nature of the
project and the main issues. There may also be merit in
checking the ES against the list of required contents set
out in the Regulations (see paragraphs 64-65 above) to gain
an initial overview. Most statements do not however deal
with the issues in the same order as the Regulations and
the initial check would therefore involve a complete
reading of the ES. In that case the time will probably be
better spent on a full review using the checklist at Annex
5.
Adequacy of environmental information
"It is not open to a planning authority to decline to
register an EIA, on the grounds that it disagrees with the
analysis or judgements contained within the ES, or because
it feels that insufficient attention has been paid to
specific topics. In such circumstances it will be necessary
for the planning authority to require the provision of
further information or evidence to back up unsubstantiated
statements and conclusions." (
Evaluation of Environmental Information for Planning
Projects - A Good Practice Guide, DOE, 1994).
EIA (Scotland) Regulations1999, Schedule 4
Circular 15/1999, paragraphs 114-116.
Reviewing the Environmental Statement
85. Evaluation begins with the planning authority's and
consultees' review of the ES. This should be undertaken as
soon as the application is registered. If the EIA has been
of a high quality and is well reported in the ES, the work
of the planning authority and the consultees will mainly
amount to validating its methods, results and findings. If
however the ES has significant defects, the review will
expose them so that the applicant can be asked to provide
further information.
86. The purpose of the review is to:
- provide the case officer with a full understanding
of the project, the expected impacts and the mitigation
measures;
- identify if additional information or analysis
should be requested from the applicant;
- identify specific issues on which the views of
consultees should be sought;
- establish an initial view on the key environmental
issues prior to the receipt of views from
consultees;
- begin consideration of any planning conditions
which may be needed.
87. To validate the findings of the ES the case officer
has to approach it with a questioning mind. For example,
are the conclusions supported by the detailed studies or
are they only assertions? Is the ES internally consistent?
Does it 'ring true'? The detailed examination of the ES has
to be thorough so that the professional views of the case
officer are soundly based. This will require time and
attention to detail.
88. The ES can be reviewed under 5 headings:
- Elements of the Project: Does the ES
explain the main components of the project and the main
effects?
- Policy Framework: Is attention drawn
to designated areas and development plan policies, and
how much significance is attached to each?
- Environmental Effects: What potential
effects are identified and how much significance is
attached to them?
- Mitigating Measures: Has a description
been given of measures to prevent, reduce and offset
any significant adverse effects?
- Risks and Hazardous Development: Have
any risks or hazards been identified and if so what
preventative measures are proposed?
EIA (Scotland) Regulations1999, Schedule 3.1 (f)
89. To assist in this, and in the management of the
whole evaluation process, an extensive checklist based on
the 5 headings is attached at Annex 5. It provides a
convenient way of recording and summarising the views of
various consultees as well as the case officer. Alternative
approaches to review include the Lee-Colley Review Package,
the Institute of Environmental Assessment Method and the
EIA Review Checklist prepared by Environmental Resources
Management for the European Commission (see bibliography).
Some planning authorities consider it appropriate to enlist
the help of a consultant or other body to review the ES.
90. During the review the case officer will identify those
issues on which advice from specialists within the council
(e.g. archaeology, ecology, conservation, landscape,
design, environmental health) has to be sought. The review
may also identify issues on which they must have the
specific views of the statutory consultees, and although
general consultation will already be underway, the
consultee should be advised of the specific issue. The
advice from all these sources will almost always be
sufficient but exceptionally the planning authority will
have to consider the appointment of its own consultant on a
specialised topic.
Requests For Further Information
91. If an ES is inadequate the planning authority are
able to require the developer to submit further information
and give it the same publicity and consultation as the
initial statement over a 28 day period. This is less likely
to occur if the EIA has been thoroughly scoped, the
environmental studies rigorously carried out and the ES
presented to a good standard.
EIA (Scotland) Regulations1999 Reg. 19
92. In practice planning authorities have used their
discretion to decide whether the information required
amounts to "environmental information" as defined in the
Regulations. There can be no definitive advice on whether
to advertise but acting within the terms of the Regulations
the questions to consider include whether the
information:
- is of a minor factual nature, such as a correction,
which does not change the project or its expected
impacts?
- is likely to affect the concerns of a consultee or
an interest group?
- has implications for other parts of the ES?
EIA (Scotland) Regulations1999 Reg. 2 (1)
The Planning Report and Decision
93. Following the review of the ES, the case officer's
understanding will have been supplemented by the views of
consultees and any further information from the applicant.
It is likely that a number of the potential impacts will be
subject to mitigation measures, especially if the impacts
have been considered early in the design process, and the
key parties may well have reached agreement about the
suitability of such measures. Experience shows that there
will usually be a small number of major issues, perhaps
only one, on which the acceptability of the project hinges.
These major issues should be highlighted in the planning
report, drawing on the ES.
94. The planning authority's evaluation of the
environmental information will narrow down any
uncertainties over the potential impacts and suitable
mitigation measures, but some may still remain. In this
situation the precautionary principle will be relevant.
The Precautionary Principle - the principle that authorities should act prudently
to avoid the possibility of irreversible environmental
damage in situations where the scientific evidence is
inconclusive but the potential damage could be
significant.
It applies particularly where there are good grounds for
judging either that action taken promptly at comparatively
low cost may avoid more costly damage later, or that
irreversible effects may follow if action is delayed.
95. All planning applications must be determined in
accordance with the development plan unless material
considerations indicate otherwise. Providing it serves a
planning purpose, any information from the EIA process may
be material and considered alongside the provisions of the
development plan.
96. The implementation of the matters contained in the
environmental statement, including any mitigation measures,
has to be stated explicitly as part of the planning
permission. For some measures it will be appropriate to do
this by specifying them in writing as part of the planning
application. For others it will be necessary for the
planning authority to attach them as conditions or include
them in a planning agreement under Section 75 of the Town
and Country Planning (Scotland) Act 1997. The same is true
for other measures which the planning authority wish the
developer to implement, and any other matters they wish to
control, for example in response to the concerns raised by
a consultee. A general condition which says in effect that
the matters referred to in the ES should be implemented
should not be used and could be misleading when the ES has
been supplemented by further information. Further
information on planning conditions is contained in SODD
Circular 4/1998
The Use of Conditions in Planning Permissions. It
states that as a matter of policy conditions should only be
imposed where they are necessary, relevant to planning,
relevant to the development to be permitted, enforceable,
precise and reasonable in all other respects. Policy and
advice on planning agreements is set out in SODD Circular
12/1996.
Circular No. 15/1999, Paragraphs 123-127
97. For planning applications where there is an EIA the
planning authority must inform the public and consultees of
their decision (refused or granted). A statement has also
to be made available to the public which includes the
decision, the main reasons and considerations on which it
was based and a description of the main mitigation
measures. This is an opportunity for the planning authority
to set the environmental issues in context. The Committee
Report may provide the basis for this, especially when it
contains the decision notice, a summary which gives the
development plan position, the main material considerations
(including the EIA), and the mitigation measures.
Management Issues
98. Planning applications with associated EIAs will
almost always be for major projects and will warrant the
direct attention of a senior member of staff as case
officer. For projects with very complex or large scale
impacts,
Evaluation of Environmental Information for Planning
Projects - A Good Practice Guide, DoE (1994) suggests
that a small "review panel" should be formed with officers
from other relevant departments including environmental
health and technical services
99. Planning applications involving EIA are relatively
rare and planning authorities may therefore find it useful
if one member of staff is given special responsibility for
developing and maintaining an expertise in EIA and
providing advice to other members of staff and case
officers.
100. For most applications it will be clear at an early
stage in the development control process whether EIA is
required. Case officers should however be prepared to
reconsider the position during processing, particularly if
new information is made available from consultees.
101. Planning authorities may wish to consider whether
they have appropriate delegation procedures in place to
provide officers with the authority to make decisions on
the need for EIA and scoping, within the timescales set out
in the Regulations.
EIA (Scotland) Regulations1999, Regs. 5(5) & 10(4)
Development Plans
102. Applications for planning permission have to be
determined in accordance with the development plan unless
material considerations indicate otherwise (an important
material consideration will be the EIA). The depth of study
involved in an EIA is likely to identify information which
was not available during the preparation of the development
plan, especially mitigation measures which will enable the
development to proceed without adverse environmental
effects. Structure plans and local plans should therefore
refer to EIA and the role it plays in the development
control process. More detailed references can be made under
a specific topic such as waste disposal or opencast
coal.
Other EIA regimes
103. The EIA Directive includes many types of project
which are not controlled through the planning system, for
example "projects for the restructuring of rural land
holdings". Separate Regulations apply to these projects and
specify which organisation (i.e. the "competent authority")
is responsible for operating them. Some are included in
Scottish Regulations and some have separate GB
Regulations.
104. The Environmental Impact Assessment (Scotland)
Regulations 1999 include provisions for:
Town & Country Planning
Roads and Bridges
Land Drainage
105. Separate Regulations will be issued for projects
not included in the list above but which may still be
subject to environmental impact assessment. Such projects
include those falling into the following categories:
Forestry
Marine Fish Farming
Ports & Harbours
Uncultivated land
Electricity
Pipeline Works
Extraction of Minerals by Marine Dredging
Offshore Oil and Gas
Public Gas Transporters
Conclusions
106. The environment is complex. It includes the human
population, fauna, flora, soil, water, air, climatic
factors, material assets (including the architectural and
archaeological heritage), landscape, and the way these
interact with each other. Consequently evaluating the
impact of a project on the environment is often an
elaborate technical exercise, requiring the collection,
presentation and analysis of a large amount of information,
the identification of involved issues and a consequential
specification of mitigation measures. Studies should be
focussed on the key issues on which the acceptability of
the project rests, and not be unnecessarily elaborate. EIA
provides a structured approach to the complicated task of
understanding the likely environmental effects, and taking
them into account in:
- the design of the project; and
- the determination of the planning application.
107. Central to the EIA process is the design, operation
and monitoring of effective mitigation measures. The most
effective mitigation measures are those which prevent the
creation of adverse effects at source. The second best are
those which reduce the effects, and the third best are
those which offset the effects by compensatory action. The
aim should be to prevent the effects if possible and only
then consider other measures.
108. Environmental issues must be seen alongside other
concerns and considerations, but EIA should nevertheless
play a key role in decision making at all stages of a
project, bringing benefits to applicants, consultees, the
public, interest groups, and planning authorities. There
has been considerable experience of EIA in Scotland over a
period of nearly thirty years. This PAN, which is issued to
coincide with the introduction of revised Environmental
Impact Assessment Regulations draws on this experience and
highlights best practice in the conduct of EIA.
Note
109. Enquiries about the contents of this planning
advice note should be addressed to Neil Henderson, Scottish
Executive Development Department, Planning Services, Room
2-H, Victoria Quay, Edinburgh EH6 6QQ (Tel: 0131-244 7550,
e-mail:
neil.henderson2@scotland.gov.uk).
Further copies, together with other PANs, can be obtained
by contacting Lynn Jameson at the same address (Tel:
0131-244 7543, e-mail:
lynn.jameson@scotland.gov.uk).
NPPGs and Circulars are available from David Love, Scottish
Executive Development Department, Planning Division, also
at the same address (Tel: 0131-244 7066 e-mail:
david.love@scotland.gov.uk).
110. In addition, this PAN, along with other planning
series documents, is accessible within the Scottish
Executive web site at
www.scotland.gov.uk/planning.
Environmental statements received up to February 1999 are
listed at Annex 4 and are available for examination by
arrangement with the Scottish Executive Library, K Spur,
Saughton House (Tel:
0131 - 244 4564).
Bibliography
Commission of the European Communities
(1992)
Towards Sustainability: The EC Fifth Environment Action
Programme 1993-2000.
Commission of the European Communities
(1993),
Report On The Implementation Of Directive 85/337/EEC
And Annex For The United Kingdom. ISBN
92-77-52778-1.
Commission of the European Communities
(1994),
Environmental Impact Assessment _ Review
Checklist.
Commission of the European Communities
(1996),
Guidance on Scoping.
Commission of the European Communities
(1996),
Guidance on Screening.
Department Of The Environment (1989),
Environmental Assessment- A Guide to the Procedures,
London, HMSO. ISBN 0-11-752244-9.
Department Of The Environment (1991),
Monitoring Environmental Assessment and Planning,
London, HMSO. ISBN 0-11-752436-0.
Department of the Environment (1994),
Good Practice on the Evaluation of Environmental
Information for Planning Projects- Research Report,
London, HMSO. ISBN 0-11-752990-7
Department of the Environment (1994),
Evaluation of Environmental Information for Planning
Projects - A Good Practice Guide, London, HMSO. ISBN
0-11-7530432990-73.
Department Of The Environment (1995),
Preparation Of Environmental Statements For Planning
Projects That Require Environmental Assessment- A Good
Practice Guide, London, HMSO. ISBN 0-11-753207-X
Department Of The Environment (1996),
Changes In The Quality Of Environmental Statements For
Planning Projects - Research Report, London, HMSO.
ISBN 0-11-753269-X
Department Of The Environment,
Transport and the Regions(1997), Mitigation Measures in Environmental
Statements, London, HMSO. ISBN 1-85112-050-5
EC Council,
Directive On The Assessment Of The Effects Of Certain
Public And Private Projects On The Environment
(85/337/EEC)
EC Council,
Directive (97/11/EC) amending Directive
85/337/EEC
Environmental Impact Assessment (Scotland)
Regulations 1999 (SSI 1/1999), The Stationery
Office, ISBN 0-11-059107-0
Institute of Environmental Assessment
(1995),
Guidelines for Baseline Ecological Assessment
Institute of Environmental Assessment
(1995),
Guidelines for Landscape and Visual Impact
Assessment
Lee, N. and Colley, R. (1990),
Reviewing the Quality of Environmental Statements,
Occasional Paper 24, Dept. of Planning and Landscape,
University of Manchester
Lee, N. and Colley, R. (1991),
Reviewing the Quality of Environmental Statements:
Review Methods and Findings, Town Planning Review,
62,2.
RSPB (1995),"
Wildlife Impact _ the treatment of nature conservation
in environmental assessment", The RSPB,
Scottish Executive Development Department Circular
15/1999,
"Environmental Impact Assessment (Scotland) Regulations
1999"
Scottish Office Development Department Circular
25/1998,
"Review Of Old Mineral Permissions And Environmental
Impact Assessment: Notes For Guidance"
Scottish Office Environment Department Circular
6/1995,
"Habitats and Birds Directives"
Glossary
The following are explanations of terms used in the PAN
and annexes, not definitions
Baseline studies | Studies of existing environmental
conditions and trends which are designed to
establish the baseline conditions against
which any future changes can be measured or
predicted. |
"Do-nothing" scenario | The predicted future environmental
conditions which would exist in the absence
of the development. |
The Regulations | The Environmental Impact Assessment
(Scotland) Regulations 1999. |
EIA Directive | Directive 85/337/EEC (as amended by
Directive 97/11/EC) on the assessment of
certain public and private projects on the
environment. |
Environmental effect /
environmental impactenvironmental
impactenvironmental impactenvironmental impact | In this PAN, except where the context
indicates otherwise, the words impact and
effect have been used interchangeably. |
Environmental Impact
Assessment (EIAAssessment (EIAAssessment (EIAAssessment (EIA[Also known as
) Environmental
Assessment (EA)] | A process by which information about the
environmental effects of a project is
collected, impacts predicted and mitigation
identified, both by the developer and from
other sources, and taken into account by
the relevant decision making body (e.g. the
planning authority) before a decision is
given on whether the development should go
ahead. |
Environmental Statement
(ES | A document, or documents, which sets out
the developer's assessment of the likely
effects of the project on the environment
including mitigation measures and which is
submitted in conjunction with an
application for planning permission. |
Mitigation1 | A process, action, schedule or any other
thing designed to prevent, reduce or offset
adverse environmental impacts likely to be
caused by a development project. |
Pathways | The routes by which impacts are
transmitted through air, water, soils or
plants and organisms to their
receptors. |
Potential impacts | Impacts which could occur in the absence
of appropriate design modifications or
preventative measures. |
Predicted impacts | Those impacts which are predicted as a
consequence of the development although the
nature and severity of their effect will be
conditioned by the scope for
mitigation. |
Receptor | A component of the natural, created or
built environment such as a human being,
water, air, a building, or a plant that is
affected by an impact. |
Scoping | An initial stage in determining the
nature and potential scale of the
environmental impacts arising from the
proposed development, and assessing what
further studies are required to establish
their significance. |
Screening | The process of determining whether a
project requires an environmental impact
assessment. |
1 In this advice measures to 'prevent' adverse effects
include measures to 'avoid' them, and measures to 'offset'
include measures to 'remedy' them.
Annex 1: SCHEDULE 1 OF THE ENVIRONMENTAL IMPACT
ASSESSMENT REGULATIONS (SCOTLAND) 1999
DESCRIPTIONS OF DEVELOPMENT FOR THE PURPOSES OF
THE DEFINITION OF "SCHEDULE 1 DEVELOPMENT"
Interpretation
In this Schedule-
"airport" means an airport which complies with the
definition in the 1944 Chicago Convention setting up the
International Civil Aviation Organisation (Annex 14);
"express road" means a road which complies with the
definition in the European Agreement on Main International
Traffic Arteries of 15th November 1975;
"nuclear power station" and "other nuclear reactor" do
not include an installation from the site of which all
nuclear fuel and other radioactive contaminated materials
have been permanently removed; and development for the
purpose of dismantling or decommissioning a nuclear power
station or other nuclear reactor shall not be treated as
development of the description mentioned in paragraph 2(2)
of this Schedule.
Descriptions of development
The carrying out of development to provide any of the
following-
1. Crude-oil refineries (excluding
undertakings manufacturing only lubricants from crude-oil)
and installations for the gasification and liquefaction of
500 tonnes or more of coal or bituminous shale per day.
2. - (1) Thermal power stations and other
combustion installations with a heat output of 300
megawatts or more.
(2) Nuclear power stations and other nuclear reactors
(except research installations for the production and
conversion of fissionable and fertile material, whose
maximum power does not exceed 1 kilowatt continuous thermal
load).
3. - (1) Installations for the
reprocessing of irradiated nuclear fuel.
(2) Installations designed-
(a) for the production or enrichment of nuclear
fuel;
(b) for the processing of irradiated nuclear fuel or
high-level radioactive waste;
(c) for the final disposal of irradiated nuclear
fuel;
(d) solely for the final disposal of radioactive
waste;
(e) solely for the storage (planned for more than 10
years) of irradiated
nuclear fuels or radioactive waste in a different site
than the production site.
4. - (1) Integrated works for the initial
smelting of cast-iron and steel.
(2) Installations for the production of non-ferrous
crude metals from ore, concentrates or secondary raw
materials by metallurgical, chemical or electrolytic
processes.
5. Installations for the extraction of
asbestos and for the processing and transformation of
asbestos and products containing asbestos-
(a) for asbestos-cement products, with an annual
production of more than 20,000 tonnes of finished
products;
(b) for friction material, with an annual production of
more than 50 tonnes of finished products; and
(c) for other uses of asbestos, utilisation of more than
200 tonnes per year.
6. Integrated chemical installations, that
is to say, installations for the manufacture on an
industrial scale of substances using chemical conversion
processes, in which several units are juxtaposed and are
functionally linked to one another and which are-
(a) for the production of basic organic chemicals;
(b) for the production of basic inorganic chemicals;
(c) for the production of phosphorous-, nitrogen- or
potassium-based fertilisers (simple or compound
fertilisers);
(d) for the production of basic plant health products
and of biocides;
(e) for the production of basic pharmaceutical products
using a chemical or biological process;
(f) for the production of explosives.
7. - (1) Construction of lines for
long-distance railway traffic and of airports with a basic
runway length of 2,100 metres or more.
(2) Construction of motorways and express roads.
(3) Construction of a new road of four or more lanes, or
realignment and/or widening of an existing road of two
lanes or less so as to provide four or more lanes, where
such new road, or realigned and/or widened section of road,
would be 10 kilometres or more in a continuous length.
8. - (1) Inland waterways and ports for
inland-waterway traffic which permit the passage of vessels
of over 1,350 tonnes.
(2) Trading ports, piers for loading and unloading
connected to land and outside ports (excluding ferry piers)
which can take vessels of over 1,350 tonnes.
9. Waste disposal installations for the
incineration, chemical treatment (as defined in Annex IIA
to Directive 75/442/EEC under heading D9), or landfill of
hazardous waste (that is to say, waste to which Directive
91/689/EEC applies).
10. Waste disposal installations for the
incineration or chemical treatment (as defined in Annex IIA
to Directive 75/442/EEC under heading D9) of non-hazardous
waste with a capacity exceeding 100 tonnes per day.
11. Groundwater abstraction or artificial
groundwater recharge schemes where the annual volume of
water abstracted or recharged is equivalent to or exceeds
10 million cubic metres.
12. - (1) Works for the transfer of water
resources, other than piped drinking water, between river
basins where the transfer aims at preventing possible
shortages of water and where the amount of water
transferred exceeds 100 million cubic metres per year.
(2) In all other cases, works for the transfer of water
resources, other than piped drinking water, between river
basins where the multi-annual average flow of the basin of
abstraction exceeds 2,000 million cubic metres per year and
where the amount of water transferred exceeds 5% of this
flow.
13. Waste water treatment plants with a
capacity exceeding 150,000 population equivalent as defined
in Article 2(6) of Council Directive 91/271/EEC.
14. Extraction of petroleum and natural
gas for commercial purposes where the amount extracted
exceeds 500 tonnes per day in the case of petroleum and
500,000 cubic metres per day in the case of gas.
15. Dams and other installations designed
for the holding back or permanent storage of water, where a
new or additional amount of water held back or stored
exceeds 10 million cubic metres.
16. Pipelines for the transport of gas,
oil or chemicals with a diameter of more than 800
millimetres and a length of more than 40 kilometres.
17. Installations for the intensive
rearing of poultry or pigs with more than-
(a) 85,000 places for broilers or 60,000 places for
hens;
(b) 3,000 places for production pigs (over 30 kg);
or
(c) 900 places for sows.
18. Industrial plants for-
the production of pulp from timber or similar fibrous
materials;
the production of paper and board with a production
capacity exceeding 200 tonnes per day.
19. Quarries and open-cast mining where
the surface of the site exceeds 25 hectares, or peat
extraction where the surface of the site exceeds 150
hectares.
20. Installations for storage of
petroleum, petrochemical or chemical products with a
capacity of 200,000 tonnes or more.
Annex 2: SCHEDULE 2 OF THE ENVIRONMENTAL IMPACT
ASSESSMENT REGULATIONS (SCOTLAND) 1999.
DESCRIPTIONS OF DEVELOPMENT AND APPLICABLE
THRESHOLDS AND CRITERIA FOR THE PURPOSES OF THE
DEFINITION OF "SCHEDULE 2 DEVELOPMENT"
1 In the table below-
"area of the works" includes any area occupied by
apparatus, equipment, machinery, materials, plant, spoil
heaps or other facilities or stores required for
construction or installation;
"controlled waters" has the same meaning as in section
30A(1) of the Control of Pollution Act 1974;
"floorspace" means the floorspace in a building or
buildings.
2 The table below sets out the descriptions of
development and applicable thresholds and criteria for the
purposes of classifying development as Schedule 2
development.
Column 1
Description of development | Column 2
Applicable thresholds and
criteria |
The carrying out of development to provide any of the
following-
1.
Agriculture and aquaculture |
(a) Projects for the use of uncultivated
land or semi-natural areas for intensive
agricultural purposes; | The area the development exceeds 0.5
hectare. |
(b) Water management projects for
agriculture, including irrigation and land
drainage projects; | The area of the works exceeds 1
hectare. |
(c) Intensive livestock installations
(unless included in Schedule 1); | The area of new floorspace exceeds 500
square metres |
(d) Intensive fish farming; | The installation resulting from the
development is designed to produce more
than 10 tonnes of dead weight fish per
year. |
(e) Reclamation of land from the
sea. | All development. |
2.
Extractive industry |
(a) Quarries, open-cast mining and peat
extraction (unless included in Schedule
1); (b) Underground mining; | All development except the construction
of buildings or other ancillary structures
where the new floorspace does not exceed
1,000 square metres. |
(c) Extraction of minerals by marine or
fluvial dredging; | All development. |
(d) Deep drillings, in particular- (i) geothermal drilling; (ii) drilling for the storage of nuclear
waste material; (iii) drilling for water supplies; with the exception of drillings for
investigating the stability of the
soil. | (i) In relation to any type of drilling,
the area of the works exceeds 1 hectare;
or (ii) in relation to geothermal drilling
and drilling for the storage of nuclear
waste material, the drilling is within 100
metres of any controlled waters. |
(e) Surface industrial installations for
the extraction of coal, petroleum, natural
gas and ores, as well as bituminous
shale. | The area of the development exceeds 0.5
hectare. |
3.
Energy industry |
(a) Industrial installations for the
production of electricity, steam and hot
water (unless included in Schedule 1); | The area of the development exceeds 0.5
hectare. |
(b) Industrial installations for
carrying gas, steam and hot water; | The area of the works exceeds 1
hectare. |
(c) Surface storage of natural gas; (d) Underground storage of combustible
gases; (e) Surface storage of fossil fuels; | (i) The area of any new building,
deposit or structure exceeds 500 square
metres; or (ii) a new building, deposit or
structure is to be sited within 100 metres
of any controlled waters. |
(f) Industrial briquetting of coal and
lignite; | The area of new floorspace exceeds 1,000
square metres. |
(g) Installations for the processing and
storage of radioactive waste (unless
included in Schedule 1); | (i) The area of new floorspace exceeds
1,000 square metres; or (ii) the installation resulting from the
development will require an authorisation
or the variation of an authorisation under
the Radioactive Substances Act 1993. |
(h) Installations for hydroelectric
energy production; | The installation is designed to produce
more than 0.5 megawatts. |
(i) Installations for the harnessing of
wind power for energy production (wind
farms). | (i) The development involves the
installation of more than 2 turbines;
or (ii) the hub height of any turbine or
height of any other structure exceeds 15
metres. |
4.
Production and processing of
metals |
(a) Installations for the production of
pig iron or steel (primary or secondary
fusion) including continuous casting; (b) Installations for the processing of
ferrous metals- (i) hot-rolling mills; (ii) smitheries with hammers; (iii) application of protective fused
metal coats. (c) Ferrous metal foundries; | The area of new floorspace exceeds 1,000
square metres. |
(d) Installations for the smelting,
including the alloyage, of non-ferrous
metals, excluding precious metals,
including recovered products (refining,
foundry casting, etc.); (e) Installations for surface treatment
of metals and plastic materials using an
electrolytic or chemical process; (f) Manufacture and assembly of motor
vehicles and manufacture of motor-vehicle
engines; (g) Shipyards; (h) Installations for the construction
and repair of aircraft; (i) Manufacture of railway
equipment; (j) Swaging by explosives; (k) Installations for the roasting and
sintering of metallic ores. | The area of new floorspace exceeds 1,000
square metres. |
5.
Mineral industry |
- Coke ovens (dry coal
distillation)
- Installations for the manufacture
of cement;
- Installations for the production of
asbestos and the manufacture of
asbestos-based products (unless
included in Schedule 1);
- Installations for the manufacture
of glass including glass fibre;
- Installations for smelting mineral
substances including the production of
mineral fibres;
- Manufacture of ceramic products by
burning, in particular roofing tiles,
bricks, refractory bricks, tiles,
stoneware or porcelain.
| The area of new floorspace exceeds 1,000
square metres. |
6.
Chemical industry (unless included in
Schedule 1) |
- Treatment of intermediate products
and production of chemicals;
- Production of pesticides and
pharmaceutical products, paint and
varnishes, elastomers and
peroxides;
| The area of new floorspace exceeds 1,000
square metres. |
- Storage facilities for petroleum,
petrochemical and chemical
products
| - The area of any new building or
structure exceeds 0.05 hectare; or
- more than 200 tonnes of petroleum,
petrochemical or chemical products is
to be stored at any one time.
|
7.
Food industry |
(a) Manufacture of vegetable and animal
oils and fats; (b) Packing and canning of animal and
vegetable products; (c) Manufacture of dairy products; (d) Brewing and malting; (e) Confectionery and syrup
manufacture; (f) Installations for the slaughter of
animals; (g) Industrial starch manufacturing
installations; (h) Fish-meal and fish-oil
factories; (i) Sugar factories. | The area of new floorspace exceeds 1,000
square metres. |
8.
Textile, leather, wood and paper
industries |
(a) Industrial plants for the production
of paper and board (unless included in
Schedule 1); (b) Plants for the pre-treatment
(operations such as washing, bleaching,
mercerisation) or dyeing of fibres or
textiles; (c) Plants for the tanning of hides and
skins; (d) Cellulose-processing and production
installations. | The area of new floorspace exceeds 1,000
square metres. |
9.
Rubber industry |
Manufacturing and treatment of
elastomer-based products. | The area of new floorspace exceeds 1,000
square metres. |
10.
Infrastructure projects |
(a) Industrial estate development
projects; (b) Urban development projects,
including the construction of shopping
centres and car parks, sports stadiums,
leisure centres and multiplex cinemas; (c) Construction of intermodal
transhipment facilities and of intermodal
terminals (unless included in Schedule
1); | The area of the development exceeds 0.5
hectare. |
(d) Construction of railways (unless
included in Schedule 1); | The area of the works exceeds 1
hectare. |
(e) Construction of airfields (unless
included in Schedule 1); | (i) The development involves an
extension to a runway; or (ii) the area of the works exceeds 1
hectare. |
(f) Construction of roads (unless
included in Schedule 1); | The area of the works exceeds 1
hectare. |
(g) Construction of harbours and port
installations, including fishing harbours
(unless included in Schedule 1); | The area of the works exceeds 1
hectare. |
(h) Inland-waterway construction not
included in Schedule 1, canalisation and
flood-relief works; (i) Dams and other installations
designed to hold water or store it on a
long-term basis (unless included in
Schedule 1); (j) Tramways, elevated and underground
railways, suspended lines or similar lines
of a particular type, used exclusively or
mainly for passenger transport; | The area of the works exceeds 1
hectare. |
(k) Oil and gas pipeline installations
(unless included in Schedule 1); (l) Installations of long-distance
aqueducts; | (i) The area of the works exceeds 1
hectare; or (ii) in the case of a gas pipeline, the
installation has a design operating
pressure exceeding 7 bar gauge. |
(m) Coastal work to combat erosion and
maritime works capable of altering the
coast through the construction, for
example, of dykes, moles, jetties and other
sea defence works, excluding the
maintenance and reconstruction of such
works; | All development. |
(n) Groundwater abstraction and
artificial groundwater recharge schemes not
included in Schedule 1; (o) Works for the transfer of water
resources between river basins not included
in Schedule 1; | The area of the works exceeds 1
hectare. |
(p) Motorway service areas. | The area of the development exceeds 0.5
hectare. |
11.
Other projects |
(a) Permanent racing and test tracks for
motorised vehicles; | The area of the development exceeds 1
hectare. |
(b) Installations for the disposal of
waste (unless included in Schedule 1); | (i) The disposal is by incineration;
or (ii) the area of the development exceeds
0.5 hectare; or (iii) the installation is to be sited
within 100 metres of any controlled
waters. |
(c) Waste-water treatment plants (unless
included in Schedule 1); | The area of the development exceeds
1,000 square metres. |
(d) Sludge-deposition sites; (e) Storage of sc |